• Current through October 23, 2012

(a) A contractor may appeal a Board decision to the District of Columbia Court of Appeals within 120 days after the date of receipt of a copy of the decision.

(b) If the CPO determines that an appeal should be taken, the CPO, with the prior approval of the Office of the Attorney General, may appeal the Board's decision to the District of Columbia Court of Appeals for judicial review within 120 days from the date of the receipt of the Board's decision.

(Apr. 8, 2011, D.C. Law 18-371, § 1005, 58 DCR 1185.)

HISTORICAL AND STATUTORY NOTES

Prior Codifications

2001 Ed., § 2-309.05.

Legislative History of Laws

For history of Law 18-371, see notes under § 2-351.01.